Харьковская областная государственная администрация
ABOUT THE CUSTOMER

Kharkiv Regional State Administration (KHOGA) is an executive authority in the Kharkiv region of Ukraine.

FORMULATION OF THE TASK

Modernization of the outdated power supply network and structured cable network in the conditions of non-stop operation of the customer’s divisions.

ABOUT THE PROJECT

Within the framework of reconstruction of customer’s premises, SOLTI specialists have created and put into operation a structured cabling system (SCS) and a power supply system for IT equipment. Works on installation, transfer of equipment and introduction of SCS in operation were carried out without stopping the functioning of customer services.

The construction of SCS took place in several stages, starting with the complete dismantling of old communications.

After the survey of the object, engineering and project documentation was developed and state examination of engineering documentation was completed. The received conclusion of the state expertise confirmed the validity and correctness of engineering and technological decisions taken during the design.

Thanks to the well-coordinated interaction of SOLTI specialists, all the implementation was completed in short time.

As a result, it became possible to connect all users to a single information system and provide independent power supply in the renovated premises of the customer.

Used equipment and materials

Structured cable system is constructed using:

  • passive equipment – AMP;
  • cable ducts – DKC.
SOLTI Certificates
AMP NETCONNECT
ACT-1: Specialist in creating SCS on AMP equipment
AMP NETCONNECT
ACT-2: Specialist in designing SCS AMP and conducting certification tests and the right to issue a 25-year guarantee